Washing away: Saco concerned Corps plan could increase city liability
By Gillian Graham
Staff Writer
Saco may hire a
Washington, D.C.-based law firm from to advocate for its position on how to fix
Camp Ellis beach erosion and ensure the city isn’t vulnerable to lawsuits from
property owners.
The U.S. Army Corps
of Engineers has told the city it will be required to sign a third-party
agreement that holds it responsible for maintenance of sand and rocks used to
fix erosion issues in Camp Ellis. City Administrator Richard Michaud said the
city needs to retain a Washington, D.C.-based firm to avoid signing an
agreement that the council is “extremely unlikely” to sign.
The Corps’ preferred
plan of installing a jetty spur would cost $17 million. The locally preferred
plan requires construction of a spur and three breakwater segments 1,000 feet
offshore. A fourth breakwater would be placed 400 feet off Fairhaven Avenue in
Ferry Beach, he said. The cost of that project is $40 million.
A jetty is
perpendicular to the shoreline, while a breakwater is parallel to the shore.
The breakwater structures will be made of “Volkswagen car-sized rocks,” Michaud
said.
Michaud said the
federally preferred plan would require placing 300,000 to 400,000 cubic yards
of sand on the beach, which he said is likely to wash away within two years. He
said it costs $10 per cubic yard of sand. If the city signed the agreement and
did not maintain the sand, property owners could sue the city, he said.
“This cycle could
continue indefinitely,” he said.
Any project plan
would require the same level of beach nourishment, but locally preferred plan
models indicate sand additions would be needed twice in the next 50 years,
Michaud said.
Installing a spur
plus four breakwater segments would have a “very significant beneficial effect”
on the beach when coupled with the addition of more sand would stabilize Camp
Ellis Beach, Michaud said. The public works department currently spends $50,000
to $100,000 per year to haul sand to Camp Ellis. He said that is “very
different” than spending $3 million to put down 300,000 cubic yards of sand.
Any project plan would require the same level of
beach nourishment, but locally preferred plan models indicate sand additions
would be needed twice in the next 50 years, Michaud said.
The New England district of the U.S. Army Corps of
Engineers is doing studies to find a remedy for ongoing erosion of Camp Ellis
Beach. The study is under the authority of Section 111 of the River and Harbor
Act of 1968 and is being done in response to requests from Saco and state
officials.
The Corps meets periodically with state and city
officials to discuss ongoing computer modeling efforts being conducted by the
Woods Hole Group of Massachusetts. The models examine effects of coastal
structures of wave climate, currents and erosion.
The project will exceed the $5 million statutory cap
under Section 111 authority. However Congress in 2007 waived that cap for the
project in the Water Resources Development Act, which expanded the maximum
price tag to $26.9 million.
Michaud said he anticipates Corps studies will be
done by the end of the year and the group will expect the city to sign a third
party agreement at that time to move the project forward. It would be hard to
move the project forward without support of state officials during the
permitting process, he said.
The jetty was built in 1866 to protect the navigable
channel of Saco River from sand. The jetty was extended in 1897, 1930 and 1938.
It was raised at various times through 1969.
Maine State Geologist Robert Marvinney of the
Department of Conservation said Section 111 is unique because it acknowledges a
Corps structure is causing problems in Camp Ellis. He said the Corps has
third-party agreements with other types of projects, such as harbor dredging.
The state supports finding a solution to the problem, he said.
“To the state a solution for Camp Ellis is not just
shifting the problem to the next stretch of beach,” he said.
Mayor Roland Michaud said the agreement would be a
“vulnerability” for the city as it works to bring a resolution to the Camp
Ellis problems.
“If we could find a way to eliminate the need for the
third-party agreement it’s a tremendous relief to the community, he said. “The
earlier we strike trying to get this out of the picture, the better.”
Councilor Leslie Smith Jr. suggested the city wait to
see what the Corps’ final offer for a project will be before spending money to
hire a law firm. He said the jetty spur proposed by the Corps is “way too short
and needs to go out a considerable distance to ensure the sand doesn’t keep going
to Scarborough.”
Councilor Marston Lovell expressed concern that
failure to accept the agreement would cause the Corps to walk away. He asked
about the feasibility of redesignating a federal anchorage and removing the
jetty.
Mayor Michaud said it would take an act of Congress
to do that and the cost would be “astronomical.” Shoreline Commission member
Richard Milliard said removing the jetty previously was judged impractical
because it would cause “severe” problems at Hills Beach in Biddeford.
“It seems appropriate we would hire someone if we
don’t want to give the Army Corps of Engineers some reason to walk away from
this,” Lovell said.
Councilor Jeffrey Christenbury asked Michaud if
hiring a law firm would draw attention from Maine’s Congressional delegation.
Michaud said it seems interest by the delegation in the Camp Ellis problems has
fallen off recently. The mayor said Congressional staff continues to work with
the city when possible.
George Kerr, an Old Orchard Beach resident who owns three Saco
oceanfront homes, said beach erosion was exacerbated every time the height or
length of the jetty increased. He said participating in a third-party agreement
isn’t “fair to the community.”
“We’ve been kind of patsies lately. This thing has
been going on and on and on and on because no one has taken on the Army Corps
of Engineers,” he said.
Ferry Beach resident Joe Walker said the dune in
front of his home on Fairhaven Avenue has disappeared during the past three or
four years. His home is now “basically at the high-water mark” and seawater
fills his basement during large storms.
Walker said the city should have done more years ago
to address problems in Camp Ellis and Ferry Beach. Surf Street, which runs
along the ocean, is barely passable by foot and is a “disgrace” to the city, he
said.
“It’s quite a scene down where when the ocean rolls
up the street,” he said.
Mayor Michaud said he has been working on the Camp
Ellis issue for 17 years and city officials have dealt with it even longer.
“I really think we have to continue working forward.
It’s been a tough road. It must be incredibly frustrating to live there,” he
said. “I apologize. We have tried our best as a community to get this done.
We’re not giving up. This can happen but it’s going to take a lot more work.”
Michaud, the city administrator, said he will contact
the firm Mitchell and Mitchell in Washington to get their credentials and free
structure and gauge their interest in working with Saco. He said he expects to
present that information to the council for consideration in May.
Staff Writer Gillian Graham can be reached at
282-4337, ext. 213.


Comments